Roads Report: June 2024
27 June 2024
Heavy patching works on the Oxley Highway have now been completed under the Road Maintenance Council Contracts (RMCC), with linemarking completed by Central West Linemarking.
Resealing works under the RMCC have also been completed for the Resealing Program 2023-2024 on the SH11 Oxley Highway. Linemarking is currently underway and is expected to be completed by the end of June 2024.
The mixing and stabilisation of the second kilometre of the Milawa Project (Segment 250) is underway and, weather permitting, will be sealed shortly. The entire project length is 3.65km.
Works as part of the Nevertire-Bogan Road Rehabilitation Project are currently on hold due to inclement weather, and will recommence as soon as possible.
Crack sealing on RR7515 Warren Road, guard rail replacement on RR333 Carinda Road and SR65 Old Warren Road, and culvert renewal works on RR202 Marthaguy Road have been completed.
Council's Maintenance Grader works on SR23 Gradgery Lane have been completed, with crews now moving on to SR16 Notts Road, to complete the AGRN 960 flood works by the end of June 2024.