Roads Report: January 2025

30 January 2025

Roads Report: January 2025 - Post Image

Works on SH11 – Oxley Highway

Several patches in the shoulder area of the Milawa location have been completed. In total, 32 out of 62 patches under the Heavy Patching Project have been finished, with all

completed patches scheduled for sealing in the first week of February. Additionally, four culverts on the Oxley Highway have been repaired under TfNSW funding,

and 22 culverts have been cleaned. The bleeding issues in the town area along the Oxley Highway have been resolved. Road sweeping and line marking are planned to take place in one week.


SR58 - Nevertire-Bogan Road Rehabilitation Project

A total of 8 km of road has been sealed, with line marking and guidepost placement scheduled to be arranged soon.


Flood Recovery Works

Flood recovery works are currently underway on RR333 – Carinda Road, SR36 – Gibson Way, and SR12 – Lemongrove Road. So far, 10 patches on Carinda Road have been fully completed. Additionally, 3 patches on Carinda Road, 1 patch on Gibson Way, and 3 patches on Lemongrove Road are scheduled for sealing soon.


Resealing Works

The Resealing Works have been completed on the following Roads:

1) Narromine Street, Nevertire Town

2) SR58 - Nevertire Bogan Road, Segment 14

3) SR59 - Tottenham Road, Segment 22

4) RR347 - Collie Trangie Road, Segment 0

5) SR35 - Collie Bourbah Road, Segment 6

6) SR65 - Old Warren Road, Segment 6

7) SR27 - Bullagreen Road, Segment 2

8) SR12 - Lemongrove Road, Segment 0

9) SR5 - Buckiinguy Road, Segment 12