Road Report - July 2022

27 July 2022

Road Report - July 2022  - Post Image

Recent Works

Grading: Tabratong Lane, Buddabadah Road, Kianga-Marebone Road, Old Warren Road, Pigeonbah Road, Ringorah Road, Rothsay Road and Drungalear Road.

Signs and Guideposts: Tottenham Road, Nevertire-Bogan Road, Thornton Road, Wambianna Road, Bourbah Road, Warren Road and Marthaguy Road.

Slashing: Bullagreen Road, Warren Road, Pineclump Road, Collie-Trangie Road and Collie Road. 

Patching and repair: Marthaguy Road, Carinda Road and Warren Road.


Road Maintenance and Construction Schedule 

Upcoming maintenance grading and rehabilitation works scheduled for August/September 2022 include:

  • Buddabadah Road, Tyrie Road, Dandaloo Road, Marthaguy Road, Deacon Drive, Old Warren Road, Pigeonbah Road, Castlebar Road, Bundemar Road, Merrigal Road, Drungalear Road, Hatton Lane and Stephens Road. 

Road maintenance works may be subject to change with any inclement weather.

 

Capital Works in Progress

  • Construction for Ellengerah Road Segments 22, 24 and 26 is complete. This $1.7M project is jointly funded with $698,771 from Fixing Local Roads Round 2, $174,693 in Council Contribution, $211,587 Local Roads and Community Infrastructure Program Phase 2, and $634,762 from Fixing Local Roads Round 3. 
  • Construction on Old Warren Road Segments 26 and 28 is complete, further works are subject to a variation claim. A variation claim will allow for the construction of an additional 1-1.5km. This $1.6M project is jointly funded with $1,259,960 from Fixing Local Roads Program Round 3, $296,147 from Local Roads and Community Infrastructure Program Phase 2 and $123,840 Local Roads and Community Infrastructure Program Phase 3. 
  • Rehabilitation to the Collie-Trangie Road Regional Road No.347 (Segments 14 and 16) is now complete, apart from a final seal on the last 3km. This work is funded through unspent 2020/21 Transport for NSW’s REPAIR Grant.
  • Remarking of school zones 40km/h speed limit and dragon's teeth is practically complete. This project is funded by the Federal Road Safety (NSW) Program-School Zone Infrastructure Sub-Program Round 2 (Tranche 2 and Tranche 3).
  • Warren kerb and gutter replacement across multiple streets is scheduled for completion this month. Lengths have changed due to costs.
  • Investigation and design work for the CBD Improvement Program has commenced.

Back to Media Releases