Roads Report: November 2025

06 November 2025

Roads Report: November 2025  - Post Image

Road upgrades are rolling ahead across Warren Shire, with several key projects reaching completion and others set to deliver safer, smoother travel for our community.

Flood damage and maintenance grading has been completed on Bundemar Road (SR68), Wambianna Soldiers Road (SR77), Drungalear Road (SR26), Ringorah Road (SR48) and Wyndabyne Bridge Road (SR52).

Crews are now working on Tabratong Lane (SR56) and Gradgery Lane (SR23), with upcoming works planned for Oxley Road (SR1), Canonba Road (SR3) and Gibson Way (SR36).

Under the Towards Zero Safer Roads Program, works continue on Carinda Road (RR333) with all works completed on Segments 6,14,16 and 18.

On Marthaguy Road (RR202), line marking of 4km of reconstructed road is now complete.  Work on the next 6km is temporarily paused while crews complete Heavy Patching on the Oxley Highway (SH11) and reconstructing the Castlebar- Oxley Hwy Intersection.

Contractors are also finalising flood damage repairs on the Ewenmar Waste Depot Access Road, following similar works at the Animal Shelter and electronic signage will be installed on Bundemar Road (SR68) and Wambianna Road (SR66) in November 2025.

Reseal preparation has also been completed on several roads, with bitumen works planned for December 2025, while roadside slashing has been carried out across multiple rural roads, improving visibility and safety.